Timeline for Milestones |
|
May 2003 |
21 - Project Handed over to
project guide as a full functional
software package. |
|
February 2003 |
| 25 - Shyam handed over the
project to Nandan with a
prototype of Desktop agent. |
|
September 2002 |
| 20 - Project was distributed
among Nandan and Shyam. |
|
July 2002 |
| 25 - Project started as
M.Tech. Project. |
| |
|
This Week
- Installable version of Web and
Desktop agent handed
over to project guide.
- Source code and related resources are submitted to
department library and project guide.
|